Skip to content
Home
About Us
About Us
Valued Clients
Environment and Sustainability
Our Services
Asset Management
Bespoke Preventative Maintenance Programmes
Breakdown and Emergency Service
Chillers
Commercial Installation
Reactive Service
Service and Maintenance
Cool Automation
BMCS
Projects
Contact
Menu
Home
About Us
About Us
Valued Clients
Environment and Sustainability
Our Services
Asset Management
Bespoke Preventative Maintenance Programmes
Breakdown and Emergency Service
Chillers
Commercial Installation
Reactive Service
Service and Maintenance
Cool Automation
BMCS
Projects
Contact
Project Description
Central Chilled Water Plant Upgrade
Demolition and removal of the complete chilled water plant from the roof being level 28 of the Stamford Marque Apartments
Design & Build a complete new chilled water plant in a very confined space
11 x AERMEC chiller modules delivered to the roof
Complete new steel chiller platforms with inertia springs to ensure no noise to the level 27 apartment below
The modules were built into 2 banks of
Chiller No.1 containing 6 modules
Chiller No.2 containing 5 modules
New Grundfoss chilled water pumps
Upgrade the electrical switchboard
Provide complete BMCS for the new chiller plant
ENQUIRY NOW